2009-2014: Clapham Junction station improvements

3 mins read
An artist's impression of the new Brighton Yard entrance at Clapham Junction station which will provide step-free access into the station and better facilities, and help reduce congestion in the station subway.

For those who remember the proposal to build two skyscrapers at Clapham Junction station in 2009, it is also interesting to look again at the arguments used by the developers:

Scale model of the twin towers at Clapham JunctionThe proposals will help regenerate the Town Centre and will transform the station. This is once in a life time opportunity, it the plans are not supported we will face years of continued dreadful conditions at the station.

In May 2009, the proposal was withdrawn, with the help of the hundreds local residents who sent more than 700 letters of objection to the Council, and signed petitions to refuse the scheme.

So, as the developers warned, has the station been doomed since the failure of their plan, and left in a derelict state? Not at all, this is actually the opposite that happened. Lets see below all the improvement that we saw in the pas 5 years, and even more to come.

Brighton Yard

The Brighton Yard entrance, which had been out of use for over half a century, has been restored to provide an additional way into one of Britain’s busiest stations.

The new step free entrance to Clapham Junction station was officially opened in May 2011. The entrance building is based on St Johns Hill and leads directly into the station’s existing footbridge. From there passengers can access every platform via newly installed lifts or staircases.

Clapham Junction station: Brighton Yard new entrance
Clapham Junction station: Brighton Yard new entrance (Wikipedia)

Combined with the lifts, new ticket facilities, travel information screens and new shops,  it marked the completion of a  £14.5m makeover for the station. That upgrade was funded by Department for Transport, South West Trains, Wandsworth council, Transport for London, Network Rail and the Railway Heritage Trust

Lifts

Funded through the government’s Access for All programme, the creation of the step-free route into the station and from the over-bridge to all platforms made the station fully accessible for everyone (particularly those with reduced mobility, heavy luggage or young children).

The installation of glazed passenger lifts was achieved in May 2011 (although they later added an additional lift from Grant Road entrance to platform 1).

CJ station - Lift P 11-12 - nationalrail.co.uk
Lift platform 11 and 12  (nationalrail.co.uk)

Canopy

New canopies have been installed on main platforms from 2011.

New canopy installed in June 2011
New canopy installed in June 2011

Platform 10 (one of the busiest for trains going to Waterloo station at rush hour) as been revamped in 2012-2013.

Canopy on platform 10
Canopy on platform 10

New entrance for Grant Road

Clapham Junction station entrance on Grant Road had major refurbishment in 2012 in order to accommodate the overground line extension. A new lift gives a step free access to the platforms.

 

New entrance for Grant Road
New entrance for Grant Road

Platform 17 strengthening (on-going)

Network Rail has submitted its plan for platform extension: Platform 17 will be straighten and extended to accommodate longer trains. Network Rail will re-align the platform by building a “balcony-type” platform over the pavement on the station approach, with an emergency staircase at the end.

View of Platform 17 from Station Approach
View of Platform 17 from Station Approach

Larger entrance for St John’s Hill (to be started)

As they re-align platform 17, Network Rail will use the opportunity to move the Platform 17 staircase to free space in the under-path and enlarge the ticket barriers. Instead of the current 7 ticket barriers, we will have 11. With more than 50% increase it will make a big difference, especially at rush hours.

View from internal ticket gate, shopping centre entrance
View from internal ticket gate, shopping centre entrance

In project: ticket-free way through the station and more plans

  • Network Rail are developing plans for Grant Road.
  • They want to install an exit down to street level on the Grant Road side from the high level gantry passageway across the platforms.
  • They know they need to restore/allow a ticket-free way of going through the station from north to south, and are trying to see what they might do in this regard.

As we wrote in January 2009, the best way to get the station improved: To refuse the planning permission. You can see the result now and also remember it next time we have a promise to get a “once in a life time opportunity“!

Do you think what we are doing is helping the community and you want to encourage us to do more?

Your help means we can spend more time researching stories, talking to contacts, sitting through meetings and writing stories. Any money given will support community and public interest news and the expansion of our coverage in area of Clapham Junction. Battersea, Wandsworth and around.

Support us, help us to expand: subscribe to CJI with a monthly donation

Donate

Monthly amount needed to make it sustainable:

We'd be interested to hear what kind of articles you would like to see more of on the site – send your suggestions to the editor.

CJI editor and Clapham Junction Action Group co-founder and coordinator since 2008, Cyril has lived in Clapham Junction since 2001.
He is also funder and CEO of Habilis-Digital Ltd, a digital agency creating and managing websites and Internet solutions.