Is Peabody trying to get it all wrong until the end? It’s with disbelief that local residents saw the new advertising board that Peabody & Mount Anvil have placed on…
Continue Reading »Phase 3 of the Peabody project is currently underway, as announced last June. Piling is scheduled to commence next week, continuing until mid-November, and main excavation is expected to conclude…
Continue Reading »More than a year after receiving planning permission from Wandsworth Council, just prior to the election, Peabody is now starting on the third and final phase of their redevelopment in…
Continue Reading »The Planning Application Committee meeting on Tuesday 26th of April 2022 was as many other meetings in appearance. However, seen a few weeks later, it was very special in several…
Continue Reading »Did anyone at Peabody board level ever care about the fate of the to-be-removed market rent tenants? At least Tony Bird does. This Independent Housing Adviser/Consultant was approached by concerned…
Continue Reading »The most interesting part of the discussion we had on the phase 3 plan for Peabody’s development in St Johns Hill was the answer to CJAG simple question: “What will…
Continue Reading »The change announced in April 2012 has now materialised. It confirmed the previous announcement that Peabody has selected Mount Anvil as its joint partner for the final phase. As the initial…
Continue Reading »More than ten years after the initial scheme was approved by Wandsworth Council (with a lot of controversy, as officers mislead the committee and the vast majority of the local…
Continue Reading »After more than 6 months of complaints from local residents, Peabody have announced that they were prepared to offer an independent building survey undertaken by a building surveyor and structural…
Continue Reading »“At the start of it there were a lot of mini earthquakes. Now it seems like there are tiles shifting and cracks appearing“. Hence started the email from one of…
Continue Reading »